Critical Path Method: Calculate and Optimize Your Schedule
Generate a follow-up sub-lesson on any aspect of this topic
Critical Path Method: Calculate and Optimize Your Schedule
TLDR;
- One task with only a week of slack can turn a harmless two-week slip into a late launch.
- Two forward and backward passes reveal a hidden 19-week path running right behind the 20-week critical one.
- Crashing one activity helps once, then stops helping, and fast tracking shifts the risk elsewhere.
The launch review was set for week 20, and the team reported green. Then the design review for activity B ran two weeks over, and nobody escalated it because B was “not on the critical path.” The release landed in week 21. The path was not wrong, but the team never checked how much slack B actually had. The critical path method answers that question for every activity, using durations and dependencies instead of gut feel. This guide builds one eight-activity network in weeks and uses it for every calculation, so each result feeds the next.
Every schedule calculation starts from the same few inputs. An activity is a unit of work with a duration, here always in weeks. A precedence relationship says what must happen before what, and we use finish-to-start (FS) only until fast tracking changes one link. A milestone is a zero-duration marker, such as project completion at the end of G. The calendar is simple, with continuous weeks and no holidays or resource limits.
These are the inputs that most project scheduling techniques, including CPM, hold fixed. Using one consistent network matters because you can check each number against the previous one. If float changes, you know exactly which duration or link caused it.
Here is the critical path method example in full, with every activity and predecessor.
| Activity | Duration (weeks) | Predecessors |
|---|---|---|
| A | 3 | None |
| B | 4 | A |
| C | 6 | A |
| D | 5 | B |
| E | 4 | C |
| F | 3 | D, E |
| G | 4 | F, H |
| H | 2 | B |
As a diagram, A splits into two branches. B feeds D and H, and C feeds E. D and E merge at F, and F and H merge at G, which ends the project. Ask which task cannot move without moving the end date. The answer is already hiding in the longest chain here, but we will prove it with arithmetic. Explore the network before calculating anything:
The forward pass finds the earliest each activity can start (ES) and finish (EF). Rules are short. An activity with no predecessor starts at week 0, EF equals ES plus duration, and ES equals the largest EF among all predecessors.
Walk it through. A runs 0 to 3. B and C both start at 3, so B is 3 to 7 and C is 3 to 9. D follows B, so 7 to 12. H also follows B, so 7 to 9. E follows C, so 9 to 13. F waits for both D (12) and E (13), so it starts at 13 and ends at 16. G waits for F (16) and H (9), so 16 to 20.
The merge at F is where people slip. Take the latest predecessor finish, never the average or the first. The forward pass gives a project duration of 20 weeks.
The backward pass finds the latest each activity can start (LS) and finish (LF) without delaying the project. Start from the end, setting G’s LF to 20. LS equals LF minus duration, and LF equals the smallest LS among successors.
G is 16 to 20. F must finish by 16, so F is 13 to 16. D must finish by 13, so D is 8 to 13, and E must also finish by 13, so E is 9 to 13. H must finish by 16, so H is 14 to 16. C must finish by 9, so C is 3 to 9. B has two successors, D (LS 8) and H (LS 14), so its LF is 8 and it runs 4 to 8. A takes the smaller of B’s 4 and C’s 3, so A runs 0 to 3.
Mirror the earlier rule here. Where paths split, take the smallest successor LS.
Total float is how long an activity can slip without delaying the project, calculated as . Free float is how long it can slip without delaying any successor’s earliest start, calculated as the smallest successor ES minus the activity’s EF.
Total float is 1 for B (4 minus 3) and 1 for D (8 minus 7), 7 for H (14 minus 7), and 0 for A, C, E, F, and G. Free float differs. B has 0, because H and D both start at week 7 right after it. D has 1, because F starts at 13 and D finishes at 12. H has 7, because G starts at 16 and H finishes at 9.
Shared Float TrapTotal float belongs to the path, not the activity. If B uses its 1 week, D loses its float too.
Now try the calculations yourself on the network:
With float calculated, critical path analysis is a read-off. Activities with zero total float form the critical path, A–C–E–F–G, which sums to weeks. Any slip on these activities moves the finish date one for one.
Now look at what sits behind it. A–B–D–F–G adds up to weeks. This is a near-critical path, a path with little float that can become critical after a modest slip. B and D each carry the single week of float that separates the paths.
H is different. A–B–H–G totals only 13 weeks, so H has 7 weeks of float and can slide up to 7 weeks without touching the finish. Do not spend management attention there. Watch the 20-week and 19-week paths together, because a one-week overrun on the second turns it into a second critical path.
Run the earlier scenario on the network. B stretches from 4 weeks to 6. Its EF moves from 7 to 9, so D runs 9 to 14. F must wait for D (14) and E (13), so it starts at 14 and ends at 17. G then runs 17 to 21, and the project finishes in week 21.
The slip was 2 weeks, but the finish moved only 1. B’s total float absorbed the first week, and the second week passed straight through. The A–B–D–F–G path is now 21 weeks and is the sole critical path, while A–C–E–F–G has gained a week of float.
Set a monitoring trigger on near-critical work. Any activity with 1 week or less of float, such as B and D, gets a weekly status check, and any forecast overrun above its float is escalated at once. Test your own slips here:
Back on the original 20-week baseline, crashing shortens an activity by adding resources, at a cost per week saved. Constraints matter, so here are the options.
Always crash the cheapest critical activity first, which is C. Crashing C by 1 week cuts the path A–C–E–F–G to 19 weeks for $2,000. But A–B–D–F–G is also 19 weeks, so two critical paths now exist.
A second week of C would buy nothing, because the other path still takes 19. Further reduction requires shortening a shared activity (A, F, or G), or one activity on each path. Only G is crashable here, so G brings the finish to 18 weeks, for a cumulative cost of $7,000. Crashing is cheap until paths converge, then it gets expensive.
Fast tracking compresses the schedule by overlapping work that was planned in sequence. It adds risk, not cost, while crashing adds cost and little extra risk. Apply it to E and F by changing the link from FS to start-to-start with a 2-week lag. F can now start 2 weeks after E starts, at week 11.
But F also waits for D, which finishes at 12. So F starts at 12 and ends at 15, and G runs 15 to 19. The project finishes in 19 weeks, and D is now what holds F back, so A–B–D–F–G becomes the critical path.
Be honest about the tradeoff. F begins before E is done, so any design change or defect found late in E sends rework back into F. Fast tracking pays off where the overlapping work is low in coupling. Compare both approaches on the same network:
CPM uses one duration per activity, which suits work you have done before. PERT (Program Evaluation and Review Technique) uses three-point estimates, optimistic , most likely , and pessimistic . The expected duration is
and the variance is . If B is estimated at 3, 4, and 7 weeks, its expected duration is about 4.33 weeks, with a variance of roughly 0.44.
The network logic does not change. You still run forward and backward passes, but on expected durations. Then you sum variances along the critical path to estimate the probability of hitting a date. Choose CPM when durations are stable and the question is “what moves the finish?” Choose PERT when uncertainty is high and a sponsor needs “how likely is week 20?”
Use this sequence on any project. Build the network, run the forward pass, run the backward pass, calculate floats, flag critical and near-critical paths, test likely slips, and only then choose crashing or fast tracking. Final results for our network are below.
| Activity | ES | EF | LS | LF | TF | FF |
|---|---|---|---|---|---|---|
| A | 0 | 3 | 0 | 3 | 0 | 0 |
| B | 3 | 7 | 4 | 8 | 1 | 0 |
| C | 3 | 9 | 3 | 9 | 0 | 0 |
| D | 7 | 12 | 8 | 13 | 1 | 1 |
| E | 9 | 13 | 9 | 13 | 0 | 0 |
| F | 13 | 16 | 13 | 16 | 0 | 0 |
| G | 16 | 20 | 16 | 20 | 0 | 0 |
| H | 7 | 9 | 14 | 16 | 7 | 7 |
Take this table as a worksheet for your own project, with space for assumptions, risks, and chosen actions:
Before you compress anything, check which path you are really shortening. On your next project, list every path within two weeks of critical and decide today who watches each one.